Reviewing Construction

in #life5 years ago

P_20141119_101826.jpg

The beam work is carried out after the column work has been completed. In the project the beam system used is conventional. The beam used has a different type. Beams consist of 2 types, namely the main beam (main beam) and the beam. All beam and plate work is done directly in the planned location, starting from pembesian, formwork installation, casting to maintenance.

P_20141119_102015.jpg

Preparation phase
Measuring work, This measurement aims to regulate / ensure the flatness of the beam and plate height. In this work the theodolithe measuring plane is used.
Formwork Making, beam and plate formwork work is a single work unit, because it is carried out simultaneously. Making beam formwork panels must be in accordance with the working drawings. In cutting plywood must be careful and thorough so that the end result is in accordance with the area of ​​the plate or beam to be made. Beam work is carried out directly at the location by preparing the main material including: 5/7 cassettes, 6/12 wooden blocks, plywood boards

P_20141129_132454.jpg

Stage of Work Beams and Plates.
Work on beams and plates is done simultaneously on the base.

Block beaming, beam blocking stage is, Scaffolding with each distance of 100 cm arranged in line according to the needs in the field, both for beam and plate formwork.
Take into account the height of the scaffolding by adjusting the base jack or the U-head jack.
In the U-head, a 6/12 wooden beam is installed parallel to the cross brace direction and above the girder, the beam is mounted with a distance of 50 cm (wood 5/7) with its transverse direction, then a pair of plywood is placed as the base of the beam.
After that, the beam formwork wall is installed and locked with the elbow mounted above the suri.

Coin Marketplace

STEEM 0.37
TRX 0.12
JST 0.040
BTC 70162.45
ETH 3540.43
USDT 1.00
SBD 4.79