Access to heavy power generators

in #construction5 years ago

The task was to decommission the 11000 volt Sub Station, the access on foot was fine although the position needed a 200 tonne crane to span the housing so to remove safely... a simple 5 tonne lift... planning is the essence.

@thebigone7

55DB0ACB-EECE-47A8-8F4D-7E302346D11D.jpeg
Access to the Sub Station

B9790427-C4C5-4D1B-9068-C11D03C5732B.jpeg
Removal of telecommunications first

C6BFD97B-E8A8-42D6-A90C-D589B114978C.jpeg
Setting up the Crane

CCFB6F73-11F2-4639-A456-9078CEEE9492.jpeg
In position for the lift

7F0881E9-65E1-4306-81A2-397BC3599446.jpeg
Limiting in progress

12CC64BD-6589-4135-AB99-E8843A1A5504.jpeg
Nearly there

F50CBA02-0225-4082-9A99-6658E6E23CE3.jpeg
Touchdown

Coin Marketplace

STEEM 0.27
TRX 0.13
JST 0.032
BTC 61562.85
ETH 2891.34
USDT 1.00
SBD 3.43