how much labor and material needs for brick work?
As we know the wall is a barrier that serves to protect an area, the function of the wall is divided into two, namely as partitions and structural walls.
On this occasion we will only exemplify the calculation of brick walls that also function as partitions and supporters of the roof. The walls can be made of various materials such as paper, plywood, gypsum, bricks and so forth.
A wall can be said to be a structural wall if it serves as a roof support and does not use reinforced concrete columns as auxiliary structures, thus purely relying on the construction of brick and cement pairs.
We should know what bricks are before, in general, bricks are one of the wall-making materials and in certain jobs can be foundation.
Bricks made from clay that burned to change color to reddish to brownish, bricks itself is divided into several types, including:
Bricks made of clay with slippery surfaces that have erratic surfaces and erratic colors, this type of brick is called an ordinary brick.
Bricks made of sand and lime.
In general in Indonesia the use of ordinary bricks to be commonly used building materials, the bricks in question are ordinary bricks are printed and burned at high temperatures to obtain a dry brick.
The size of bricks commonly used in Indonesia are:
Description | Amount |
---|---|
Length | 17 - 23 cm |
Width | 7 - 11 cm |
Thickness | 3 - 5 cm |
While plastering is a layer to cover the field of buildings to be more robust, leveling the surface of the building and protect the structure of climate climates.
Plastering is divided into several uses depending on the level of flatness at the time of workmanship, the first is the rough plaster is usually used on the work of building structures, half-fine plastering which is often used in the work of the toilet, indoor outdoor indoor field and so forth, fine plastering is used to form walls and floor of the building.
Some requirements that must be fulfilled for stucco work are:
- Must have a very flat and upright surface
- Has a thickness of 11 - 16 cm
- No rupture was found due to plastering.
After we have a little reference to the walls, bricks and plastering then it's time to calculate the need in the installation work of brick and stucco bonds.
The wall we will count has a length of 8.00 m and a height of 3.50 m.
a. Brick Walls
Is known:
Description | Amount |
---|---|
Length | 8.00 m |
Height | 3.50 m |
Resolution:
Description | Amount |
---|---|
Length x Height | m2 |
8.00 x 3.5 | 28.00 m2 |
So the total wall area is 28.00 m2

b. Plastering
Solution is the same as calculating the wall area only we have to determine how many sides will be in the plaster, if the two sides of the total wall width x 2 sides (exterior and interior), so obtained answer 56.00 m2.

I use the coefficient of technical analysis in accordance with Indonesian National Standard
a. Work of Brick Wall Pairs, ½ bond mixture 1 portland cement: 4 sand pairs
To complete the work 1 m2 pair of brick walls ½ bond mixture 1 portland cement: 4 tide sand required:
Description | Amount |
---|---|
Workers | 0.300 Person per Day |
Stonemason | 0,100 Person per Day |
Foreman | 0.010 Person per Day |
Overseer | 0,015 Person per Day |
Bricks | 70.00 Pieces |
Portland Cement | 11,500 Kg |
River sand | 0.043 m3 |
To calculate the requirement according to volume mentioned above then we must make multiplication between coefficient with volume
Description | Information | Amount |
---|---|---|
Workers | 0.300 Person per Day x 28.00 m2 | 8,400 Person |
Stonemason | 0,100 Person per Day x 28.00 m2 | 2,800 Person |
Foreman | 0.010 Person per Day x 28.00 m2 | 0,280 Person |
Overseer | 0,015 Person per Day x 28.00 m2 | 0,420 Person |
Bricks | 70.00 pieces x 28.00 m2 | 1,960,000 Piece |
Portland Cement | 11,500 Kg x 28.00 m2 | 322,000 Kg |
River Sand | 0.043 m3 x 28.00 m2 | 1,204 m3 |
**Work Plastering, 1 Portland Cement: 4 Rivers Sand, 15 cm thick
To complete the work of 1 m2 pair of brick walls, ½ bond, mixture of 1 portland cement: 4 rivers sand is required :
Description | Amount |
---|---|
Workers | 0.300 Person per Day |
Stonemason | 0.150 Person per Day |
Foreman | 0.015 Person per Day |
Overseer | 0,015 Person per Day |
Portland Cement | 6,240 Kg |
Rivers Sand | 0,024 m3 |
To calculate the requirement according to volume mentioned above then we must make multiplication between coefficient with volume
Description | Information | Amount |
---|---|---|
Worker | 0.300 Person per Day x 56.00 m2 | 16,800 Person |
Stonemason | 0.150 Person per Day x 56.00 m2 | 8,400 Person |
Foreman | 0.015 Person per Day x 56.00 m2 | 0.840 Person |
Overseer | 0,015 Person per Day x 56.00 m2 | 0.840 Person |
Portland Cement | 6,240 Kg x 56.00 m2 | 349,440 Kg |
Rivers Sand | 0,024 m3 x 56,00 m2 | 1,344 m3 |

In accordance with technical analysis of Indonesian National Standard then to finish the wall work with length 8,00 m and height 3,50 m needed
Description | Amount |
---|---|
Worker | 25,200 Person |
Stonemason | 11,200 Person |
Foreman | 1,120 Person |
Overseer | 1,260 Person |
Bricks | 1.950,000 Peice |
Portland Cement | 671,440 Kg |
Rivers Sand | 2,548 m3 |
After we calculate technically it is expected to work on this wall we can minimize the emergence of factors that can cause losses in the future.
The calculation of labor and material needs in this wall work is only as an example that can be developed in accordance with the development of the times and is expected to young engineers to be more active in developing the knowledge they have.
This is all I can write on this occasion,for all the lack of writing and as a servant of God I apologize., thanks to friends who have visited my blog and provide constructive comments and to all actors "science" who willingly sacrificed for the development of science and knowledge like today.
source:
www.wikipedia.org (Portland cement)
Do you love science? then join us at steemstem using @science tags and @steemstem, you can also chat with us at steemstem chat. channel.
Best regards @kharrazi
nice research... and useful for almost everyone... coz some of have land for which this will be useful and some of us must be desiring to have :D
Thank you for stoping my friend
ur welcome :)
All this information is really awesome and will be really helpful to me when I start renovation of my house.
You can ask me if you need, i will ans as my best, thank you
good information
Thank you
Congratulations @kharrazi, this post is the seventh most rewarded post (based on pending payouts) in the last 12 hours written by a User account holder (accounts that hold between 0.1 and 1.0 Mega Vests). The total number of posts by User account holders during this period was 1664 and the total pending payments to posts in this category was $3196.08. To see the full list of highest paid posts across all accounts categories, click here.
If you do not wish to receive these messages in future, please reply stop to this comment.
Good post