The results of the week in the Duyunov project from 2.07 to 8.07.2018

Dmitry Duyunov summed up the results of the next working week, for which the project team managed:

start and test the operation of the nitrogen station, which allowed to start the assembly of laser equipment;
complete the laying of the fiber from the office to the workshop and to the laboratory;
start the installation of equipment and begin installation of video surveillance and security alarm systems (this work is planned to be completed next week).
Work continues on testing programs and techniques for testing engines. Approximately in the third decade of July, it is planned to issue data obtained during testing of engines for general industrial use.

As the work progresses in the laboratory, the team receives more and more requests for testing engines from third-party companies. Negotiations are in progress. Presumably, as early as August such services will be provided to organizations.