ULOG #008: Last Day of Operatioooons!

in #ulog6 years ago (edited)

Good evening Steem world! This is the first day of the week but this is the last day of being in the Operations Department. Despite of that, the next departments are still on-site so my skin will still be as dark as ever. 😢 image

We went to tower 4 first to check the columns if they are ready for cementing. First thing I noticed is the gravel floating above the concrete. It means that the sand did not mix properly with the cement mixture.
image

Then they are assembling the scaffolds already ready for the 2nd floor of the building
image

We also counted the steel rods of the column if they are properly placed and the number of it is okay.
image

Some spacer walls
image

And the view of the site from the 2nd floor scaffolding of tower 4
image

We also climbed the roof deck again
image
image
image
image

Soon to be elevators
image

And here is the fire exit of tower 1 from the roof deck
image

And the view of the underground of tower 3 while we are walking back the office
image

So that's all for the last day of operations. Thank you for reading!

Sort:  

ulogs is very good project...

I love this work. So detailed and articulated. Thanks for sharing.

I am me @brightfame

Coin Marketplace

STEEM 0.27
TRX 0.13
JST 0.032
BTC 62875.98
ETH 2948.16
USDT 1.00
SBD 3.55